Expect Delays: Road Construction near BMC-Foothills
Road construction is underway on Arapahoe Avenue in front of the BCH Foothills Hospital campus, which also houses the Boulder Medical Center-Foothills clinic. Work is expected to continue through late December 2025 and may impact traffic flow and cause travel delays for patients and visitors.
Please Plan Ahead
-
-
Allow extra travel time for appointments
-
Check your route in advance for detours or closures
-
Stay informed by visiting the Colorado Department of Transportation (CDOT) website
-
About the Project
The Colorado Department of Transportation (CDOT) is resurfacing Colorado Highway 7 (Arapahoe Avenue) between Cherryvale Road and 28th Street in Boulder. The project includes:
-
-
Milling and resurfacing of asphalt to improve road safety and ride quality
-
Installation of ADA-compliant curb ramps
-
Erosion control to protect nearby waterways during construction
-
In collaboration with the City of Boulder, CDOT will also implement the East Arapahoe Bus and Turn Lanes Signing & Striping Project, which includes:
-
-
Converting underused traffic lanes into shared bus and right-turn lanes
-
Enhancing bus route reliability and reducing community disruption
-
Together, these projects aim to improve accessibility, traffic flow, and safety for all travelers in the corridor.
Project Details
Schedule
-
-
Monday through Friday
-
7:00 a.m. – 7:00 p.m.
-
Weather dependent and subject to change
-
Traffic Impacts
-
-
Expect single-lane closures on Arapahoe Avenue (CO 7)
-
Overnight milling and resurfacing are expected in summer 2025
-
Detours may impact travel time
-
Speed limit reductions are in effect throughout the work zone
-
Delays up to 10 minutes are expected during work hours
-
Watch for construction vehicles entering and exiting the area
-