Expect Delays: Arapahoe Avenue near BMC-Foothills

Expect Delays: Road Construction near BMC-Foothills

Road construction is underway on Arapahoe Avenue in front of the BCH Foothills Hospital campus, which also houses the Boulder Medical Center-Foothills clinic. Work is expected to continue through late December 2025 and may impact traffic flow and cause travel delays for patients and visitors.

Please Plan Ahead


About the Project

The Colorado Department of Transportation (CDOT) is resurfacing Colorado Highway 7 (Arapahoe Avenue) between Cherryvale Road and 28th Street in Boulder. The project includes:

    • Milling and resurfacing of asphalt to improve road safety and ride quality

    • Installation of ADA-compliant curb ramps

    • Erosion control to protect nearby waterways during construction

In collaboration with the City of Boulder, CDOT will also implement the East Arapahoe Bus and Turn Lanes Signing & Striping Project, which includes:

    • Converting underused traffic lanes into shared bus and right-turn lanes

    • Enhancing bus route reliability and reducing community disruption

Together, these projects aim to improve accessibility, traffic flow, and safety for all travelers in the corridor.


Project Details

Schedule

    • Monday through Friday

    • 7:00 a.m. – 7:00 p.m.

    • Weather dependent and subject to change

Traffic Impacts

    • Expect single-lane closures on Arapahoe Avenue (CO 7)

    • Overnight milling and resurfacing are expected in summer 2025

    • Detours may impact travel time

    • Speed limit reductions are in effect throughout the work zone

    • Delays up to 10 minutes are expected during work hours

    • Watch for construction vehicles entering and exiting the area